How to Compare Granny Flat Quotes in Sydney: Scope, Allowances and Contracts

Generic conceptual image of homeowners comparing blank quote folders; not an AIVEO customer or project

How do you compare granny flat quotes in Sydney? Ask each supplier to price the same proposed dwelling on the same property, then compare the written scope line by line. A module price alone does not tell you who will pay for design, approvals, site preparation, delivery, installation, services or final handover. Treat an early figure as a starting point until the site and contract scope have been checked.

This guide is a comparison worksheet for a proposed NSW secondary dwelling. It does not quote an AIVEO price or establish that a particular block or design can be approved. For a short overview of quote scope, see our Sydney granny flat Q&A. For the first property checks, read our Sydney granny flat land guide.

Start with one brief and one set of site information

Two prices are difficult to compare if the suppliers assumed different buildings or different site conditions. Give each supplier the same address, available survey and title information, site photos, access measurements, preferred use, proposed room schedule and finish expectations. Mark anything that is still unknown. Ask them to state which measurements, ground conditions and approvals they have actually checked rather than allowing a concept drawing to stand in for a measured design.

Our Sydney modular home site checklist helps gather information about delivery access and services before you request a detailed proposal. Room layouts and dimensions on AIVEO's current concept images require design review; use a checked, site-specific drawing for a final comparison. Our Sydney floor-plan checklist explains what to request before pricing a layout.

Compare the same seven parts of the project

Ask for a written inclusions-and-exclusions schedule. The useful question in each row is: is this item included at a defined price, allowed for as an estimate, supplied by someone else, or not yet assessed?

Part of the project Questions for each supplier
Design and documents Which plan version, measured area schedule, specifications, engineering, sustainability documents and approval drawings are included? Who prepares revisions?
Site investigation Are the survey, ground or footing investigation, existing-service checks and site-specific engineering included? What remains an assumption?
Building and finishes What is supplied inside the dwelling? List kitchen, bathroom, heating or cooling, flooring, glazing, appliances, fixtures and any owner selections by model or allowance.
Delivery and installation Who pays for transport, route assessment, crane or lifting equipment, temporary access, traffic management, module joining and weatherproofing?
Groundworks and external works Are footings, excavation, drainage, retaining, stairs, decks, paths, landscaping and removal of construction waste included?
Services Who arranges and pays for electrical work, water, wastewater, any required upgrades, meters, trenching, inspections and connection fees?
Approvals and handover Who handles planning and certifier submissions, Sydney Water requirements, inspections, final certificates, defects and handover documents?

Some items may be unnecessary for your site; others may require a specialist before anyone can price them accurately. The aim is to make those differences visible before you compare totals.

Separate fixed scope, allowances and exclusions

Ask the supplier to show a subtotal for defined work, a separate list of allowances and a separate list of exclusions. In NSW residential building contracts, a prime cost item can cover a fixture that has not yet been selected, while a provisional sum can cover work that cannot yet be priced definitively. Both can affect the eventual price. The NSW Government's home-building contract guidance explains prime cost items and recommends selecting fittings and appliances before signing where possible; its model home-building contract explains provisional sums.

For every allowance, ask what quantity and quality were assumed, whether labour, delivery and GST are included, what evidence will set the final amount, and how any difference will be approved. An unusually low allowance can make a headline total look attractive while leaving a predictable cost unresolved. Ask the supplier to replace estimates with site-specific prices as information becomes available.

Ask separately about Sydney Water approval and connections

A water or wastewater connection is not the same step as approval of the building plan. Sydney Water says granny-flat building works need its building-plan approval before work starts and that plan checks, inspections, service connections or infrastructure requirements may add costs. Its connection guidance explains that a new connection has a separate application and conditions, and some work must be carried out by specified providers or licensed trades.

Ask each supplier: Who checks existing Sydney Water assets and easements? Who makes the building-plan application? Does the proposal need a new connection or an alteration to an existing private service? Who prices the work and responds if Sydney Water imposes conditions? The answer depends on your property; a generic module quote cannot settle it.

Check the builder and contract before paying a deposit

Once the scope is developed, check the contracting entity and the contract documents, not just the brochure. The NSW Government licence guide explains how to check a builder's or tradesperson's licence and that the licence must match the entity doing the work. NSW also sets requirements for written residential building contracts, plans and specifications, variation records and progress payments; review the current contract guidance before signing.

For eligible home-building work valued at $20,000 or more including GST, Service NSW says Home Building Compensation cover must be in place before the contractor takes money or starts work. Check the project-specific certificate and seek independent advice if contract terms are unclear. A draft quote is no substitute for the correct contract, insurance and final approved scope.

Seven questions to send with your quote request

  1. Which drawing revision and area schedule did you price, and which dimensions remain indicative?
  2. What site information did you inspect, and what assumptions could change the price?
  3. Which design, engineering, planning, certifier and utility applications are included?
  4. Who pays for footings, delivery, crane access, installation, external works and waste removal?
  5. Which items are fixed, which are prime cost or provisional allowances, and which are excluded?
  6. Who is the licensed contracting entity, and when will the required contract and insurance documents be supplied?
  7. What must happen before each progress payment, and how will changes in cost or time be agreed in writing?

If a proposed AIVEO G1 concept interests you, send your address, survey if available, site photos and intended use through our free land assessment. We can use those facts to identify what requires professional checking before a site-specific layout and written quote are prepared. The assessment is an initial discussion, not a fixed-price offer or approval.